How long will it take to cover XXX km, miles, square meters, feet, etc.?

In other words, if I am going to bill for a set number of days how many days is it going to take me to do the job?

To survey a 200 m x 200 m plot with data density of 1 reading/meter and line spacing of 5 meters would require a tow speed of 3.6 km/hour over 41 profile lines. That would 8.2 km of line-kilometers surveyed. At a conservative estimate of 30 minutes per kilometer that would be slightly over 4 hours of acquisition. With a turn-around time of 10 minutes per line that would add another 7 hours for a total of 11 hours. The survey could be done in 2 days. This is under the assumption that a multi-receiver system is being used and lines do not need to be repeated.